- Measure the length and width in feet and the thickness in inches. The example is a 10 × 10 ft slab, 4 in thick.
- Multiply length × width × thickness in feet: 10 × 10 × 4 ÷ 12 = 33.33 ft³.
- Add 10% waste for spills, a soft subgrade and form bulge: 33.33 × 1.10 = 36.67 ft³. That is 1.36 yd³, or 1.04 m³.
- Divide by the bag yield: 36.67 ÷ 0.60 = 61.11 bags.
- Round up to whole bags: 62 bags of 80 lb. Together they weigh 4,960 lb, so check your vehicle's payload before you load them, or have them delivered.
bags = ceil(length × width × thickness ÷ 12 × (1 + waste) ÷ bag yield)
Yield is the volume of finished concrete one bag makes when you mix it with the amount of water printed on the bag. It is not the size of the dry bag. Extra water makes the mix easier to place but weakens the concrete, so stick to the label. The calculator uses the common yields of 0.30, 0.375, 0.45 and 0.60 ft³ for 40, 50, 60 and 80 lb bags. If your bag lists a different yield, which can happen with fast-setting or specialty mixes, divide by the figure on your bag instead.
For a round pad, the volume is π × radius² × thickness. The calculator's default round pad, 8 ft across and 4 inches thick, takes 31 bags of 80 lb concrete with 10% waste.
Bags of concrete per cubic yard
A cubic yard is 27 ft³. Divide 27 by the bag yield to get the bags in one yard of concrete, then add waste if the yard is the net volume of your pour. If you already know the volume, choose “I know the volume” in the calculator and enter it in cubic yards.
| Bag size | Yield per bag | Bags per yd³ | With 10% waste | Weight of bags per yd³ |
|---|---|---|---|---|
| 40 lb | 0.30 ft³ | 90 | 99 | 3,600 lb |
| 50 lb | 0.375 ft³ | 72 | 80 | 3,600 lb |
| 60 lb | 0.45 ft³ | 60 | 66 | 3,600 lb |
| 80 lb | 0.60 ft³ | 45 | 50 | 3,600 lb |
Bag counts are rounded up to whole bags. Yields are for the mixed concrete at the water the bag calls for.
The yields scale with bag weight, so a yard of concrete takes about 3,600 lb of bags whichever size you buy. Smaller bags do not lighten the job. They split it into more, lighter lifts and more bags to open and mix.
Concrete bags for common slab and pad sizes
The table covers pads and small slabs 4 inches thick, a common thickness for patios and walks. For any other thickness, enter it in the calculator above.
| Slab or pad | Concrete incl. 10% waste | 40 lb bags | 50 lb bags | 60 lb bags | 80 lb bags |
|---|---|---|---|---|---|
| 2 × 2 ft | 0.05 yd³ | 5 | 4 | 4 | 3 |
| 3 × 3 ft | 0.12 yd³ | 11 | 9 | 8 | 6 |
| 4 × 4 ft | 0.22 yd³ | 20 | 16 | 14 | 10 |
| 3 × 5 ft | 0.20 yd³ | 19 | 15 | 13 | 10 |
| 4 × 6 ft | 0.33 yd³ | 30 | 24 | 20 | 15 |
| 4 × 8 ft | 0.43 yd³ | 40 | 32 | 27 | 20 |
| 6 × 6 ft | 0.49 yd³ | 44 | 36 | 30 | 22 |
| 8 × 8 ft | 0.87 yd³ | 79 | 63 | 53 | 40 |
| 10 × 10 ft | 1.36 yd³ | 123 | 98 | 82 | 62 |
| 10 × 12 ft | 1.63 yd³ | 147 | 118 | 98 | 74 |
| 12 × 12 ft | 1.96 yd³ | 176 | 141 | 118 | 88 |
Includes 10% waste. Each column is rounded up to whole bags on its own, so the columns are not exact multiples of each other.
Pads up to 8 × 8 ft (40 bags of 80 lb) stay under a cubic yard. From 10 × 10 ft up, the pour is more than a yard, and the calculator suggests comparing a mixer or ready-mix.
40, 60 or 80 lb bags
Every bag size makes the same amount of concrete per pound, so the choice is about handling, not material. For the 10 × 10 ft example, the total weight barely moves, from 4,900 to 4,960 lb. The number of bags you lift, open and mix changes a lot.
| Bag size | Bags needed | Weight of one bag | Total weight |
|---|---|---|---|
| 40 lb | 123 | 40 lb | 4,920 lb |
| 50 lb | 98 | 50 lb | 4,900 lb |
| 60 lb | 82 | 60 lb | 4,920 lb |
| 80 lb | 62 | 80 lb | 4,960 lb |
Includes 10% waste. Totals differ slightly only because each size is rounded up to whole bags.
- 80 lb bags mean the fewest bags and batches: 61 fewer than with 40 lb bags on this slab. They are heavy to carry and to tip into a mixer, so a hand truck or a second person helps.
- 60 lb bags are a middle ground. They take 82 bags here instead of 62.
- 40 and 50 lb bags are the easiest to lift and pour. They suit repairs, a few post holes or anyone who should not lift 80 lb. On tiny jobs they also leave less half-used mix behind. Open dry mix takes on moisture and goes hard, so seal and store leftovers dry.
- Price: compare bags by cost per cubic foot, not per bag. Divide the shelf price by the yield on the bag.
How many bags one person can mix
Hand mixing in a wheelbarrow or tub works well for a few bags at a time: post holes, a small pad, a step repair. A slab is harder. Each batch has to be placed, leveled and worked into the last one before that one starts to set. If it is not, you get weak cold joints and an uneven finish. Hot, dry or windy weather shortens that window. How fast someone mixes varies too much to give a reliable bag count, so plan the work in small batches and line up help before you open the first bag.
The calculator warns once a pour, waste included, passes 1 cubic yard. One yard is 45 bags of 80 lb, or 3,600 lb of dry mix to lift. Past that point, two options usually make more sense:
- A rented drum mixer speeds up each batch, but every bag still has to be carried, opened and poured. Plan on a crew: one person mixing, one placing and one finishing.
- Ready-mix delivery brings the whole pour at once. Small loads often carry a short-load fee, so price both ways in the concrete cost calculator, which handles order rounding and fees against bags at your local prices.
Wet concrete is caustic and can burn skin. Wear waterproof gloves, eye protection and long sleeves, and a dust mask when you pour dry mix. The bag label lists the hazards and first aid.
Post holes, footings and other shapes
This calculator covers flat slabs, round pads and a known volume. Post holes need different math: the post takes up part of the hole, and a gravel base at the bottom takes up more. The post hole concrete calculator subtracts both. With its default inputs, a 10 in hole 30 in deep with a 4 × 4 post on 6 in of gravel takes 2.7 bags of 50 lb concrete per hole, waste included.
For walls, footings, columns and steps, work out the volume in the concrete calculator, then enter it here as a known volume to convert it to bags.
Not included
- Base: the compacted gravel under a slab or pad. Size it with the gravel calculator.
- Reinforcement: rebar, wire mesh or fiber, and the control joints that keep cracks in straight lines.
- Forms and finishing: form boards, stakes, a float, an edger and curing. For the rest of the job, see the concrete and masonry calculators.
Frequently asked questions
How many bags of concrete do I need for a 10 × 10 slab?
A 10 × 10 ft slab 4 inches thick needs 62 bags of 80 lb concrete with 10% waste, or 82 bags of 60 lb or 123 bags of 40 lb. That is 1.36 yd³. At 6 inches thick it takes 92 bags of 80 lb.
How many 80 lb bags of concrete make a yard?
It takes 45 bags of 80 lb concrete to make one cubic yard, because each bag yields 0.60 ft³ and a yard is 27 ft³. With 10% waste, buy 50.
How many 60 lb bags of concrete make a yard?
It takes 60 bags of 60 lb concrete to make one cubic yard at 0.45 ft³ per bag. With 10% waste, buy 66.
How many bags of concrete do I need for a fence post?
For a 10 in hole 30 in deep with a 4 × 4 post on 6 in of gravel, one post takes about 2.7 bags of 50 lb concrete with waste. Buy 3 bags of 50 lb or 2 bags of 80 lb per post. Hole sizes vary a lot, so use the post hole concrete calculator for your hole and post count.
Should I buy 40 lb or 80 lb bags of concrete?
Both make the same concrete per pound, so a job takes about twice as many 40 lb bags: 123 against 62 for a 10 × 10 ft slab at 4 in. Buy 80 lb bags for slabs if you can lift them safely, and 40 lb bags for small jobs or when 80 lb is too heavy to handle.
How many square feet does an 80 lb bag of concrete cover?
An 80 lb bag makes 0.60 ft³, which covers 1.8 ft² at 4 inches thick before waste. A 60 lb bag covers 1.35 ft² and a 40 lb bag 0.9 ft² at the same thickness.
The formula, worked example and tables on this page are generated from the same calculation engine as the calculator, which is checked by automated reference tests. Last reviewed 20 November 2026 by the Solosoft team. Results are planning estimates, not engineering or code approval. See the calculation disclaimer.