How to calculate concrete for post holes
- Subtract the gravel from the hole depth to get the height of the concrete: 30 − 6 = 24 in.
- Work out the hole volume as a cylinder and divide by 1,728 to turn cubic inches into cubic feet: π × (10 ÷ 2)² × 24 ÷ 1,728 = 1.091 ft³.
- Subtract the part of the post that sits in the concrete. A 4×4 is 3½ in square: 3.5 × 3.5 × 24 ÷ 1,728 = 0.170 ft³, which leaves 0.921 ft³ per hole.
- Multiply by the number of posts and add 10% waste: 0.921 × 10 × 1.10 = 10.13 ft³ (0.38 yd³, or 0.29 m³).
- Divide by the bag yield and round up. A 50 lb bag makes 0.375 ft³: 10.13 ÷ 0.375 = 27.01, so you buy 28 bags. With 80 lb bags (0.60 ft³) it is 17 bags.
bags = ceil((π × (D ÷ 2)² − post area) × (depth − gravel) ÷ 1,728 × posts × (1 + waste) ÷ bag yield)
Round up the total for the whole job, not each hole. Each hole takes about 2.7 bags, so rounding every hole up to a whole bag would mean buying 30 bags instead of 28. Mix a full bag at a time and carry what is left to the next hole. The bags weigh about 1,400 lb in 50 lb bags or 1,360 lb in 80 lb bags, so plan how you will move them.
The yields used here are 0.30 ft³ for a 40 lb bag, 0.375 ft³ for a 50 lb bag, 0.45 ft³ for a 60 lb bag and 0.60 ft³ for an 80 lb bag. Some mixes yield a little more or less, so check the yield printed on your bag. For slabs and pads by the bag, use the concrete bag calculator.
Bags per hole for 4×4 posts
| Hole | Bag | 24 in deep | 30 in | 36 in | 42 in | 48 in |
|---|---|---|---|---|---|---|
| 8 in * | 50 lb | 1.2 | 1.5 | 1.9 | 2.3 | 2.7 |
| 8 in * | 80 lb | 0.7 | 1.0 | 1.2 | 1.5 | 1.7 |
| 10 in | 50 lb | 2.0 | 2.7 | 3.4 | 4.1 | 4.7 |
| 10 in | 80 lb | 1.3 | 1.7 | 2.1 | 2.5 | 3.0 |
| 12 in | 50 lb | 3.1 | 4.1 | 5.1 | 6.2 | 7.2 |
| 12 in | 80 lb | 1.9 | 2.6 | 3.2 | 3.9 | 4.5 |
Hole depth includes 6 in of gravel, so a 24 in hole holds 18 in of concrete. Figures include 10% waste and are per hole, not rounded. Multiply by your post count, then round up. * Under 2.5 times the post width; the calculator warns that the hole is narrow.
Bags per hole for 6×6 posts
| Hole | Bag | 24 in deep | 30 in | 36 in | 42 in | 48 in |
|---|---|---|---|---|---|---|
| 12 in * | 50 lb | 2.5 | 3.4 | 4.2 | 5.1 | 5.9 |
| 12 in * | 80 lb | 1.6 | 2.1 | 2.6 | 3.2 | 3.7 |
| 16 in | 50 lb | 5.2 | 7.0 | 8.7 | 10.4 | 12.2 |
| 16 in | 80 lb | 3.3 | 4.3 | 5.4 | 6.5 | 7.6 |
| 18 in | 50 lb | 6.9 | 9.1 | 11.4 | 13.7 | 16.0 |
| 18 in | 80 lb | 4.3 | 5.7 | 7.1 | 8.6 | 10.0 |
Same assumptions as the 4×4 table. * Under 2.5 times the post width. A 6×6 post displaces more concrete than a 4×4, so a wider hole matters more than the bag count suggests.
Concrete for 5, 10 and 20 posts
| Posts and hole | Concrete incl. waste | 50 lb bags | 60 lb bags | 80 lb bags | Gravel |
|---|---|---|---|---|---|
| 5 × 4×4, 10 × 30 in | 5.1 ft³ (0.19 yd³) | 14 | 12 | 9 | 1.4 ft³ |
| 10 × 4×4, 10 × 30 in | 10.1 ft³ (0.38 yd³) | 28 | 23 | 17 | 2.7 ft³ |
| 20 × 4×4, 10 × 30 in | 20.3 ft³ (0.75 yd³) | 55 | 46 | 34 | 5.5 ft³ |
| 5 × 6×6, 16 × 36 in | 16.3 ft³ (0.60 yd³) | 44 | 37 | 28 | 3.5 ft³ |
| 10 × 6×6, 16 × 36 in | 32.6 ft³ (1.21 yd³) | 87 | 73 | 55 | 7.0 ft³ |
| 20 × 6×6, 16 × 36 in | 65.2 ft³ (2.42 yd³) | 174 | 145 | 109 | 14.0 ft³ |
Holes are diameter × depth with 6 in of gravel in each. Bag counts are rounded up for the whole job and include 10% waste. Gravel is the loose volume in the hole bottoms.
How wide and how deep to dig
A common rule of thumb is a hole about 3 times the width of the post. That is 10.5 in for a 4×4, so a 10 or 12 in auger, and 16.5 in for a 6×6. A wider hole puts more concrete around the post and spreads the load over more soil.
Depth is often given as about a third to a half of the post's height above ground. For a 6 ft fence that is 24 to 36 in. A 10 in hole 36 in deep takes about 3.4 bags of 50 lb concrete, or 2.1 bags of 80 lb. Where the ground freezes, holes usually go below the frost line so frost cannot lift the post. These are common rules, not code. Your local code and building department set the frost depth and any footing rules for decks and tall fences, and deck plans often specify the hole size outright.
In the US, call 811 a few days before you dig so buried utility lines are marked.
What the calculator's warnings mean
- Narrow hole: the calculator warns when the hole is under about 2.5 times the post width. An 8 in hole around a 4×4 is only 2.29 times the post width, so it gets the warning. The default 10 in hole is 2.86 times and does not. Widen the hole rather than relying on a thin ring of concrete.
- Shallow concrete: the calculator warns when there is less than 18 in of concrete above the gravel. A 24 in hole on 6 in of gravel leaves exactly 18 in, which passes. A 20 in hole leaves 14 in and gets the warning. Check your frost depth before going shallower.
- Post does not fit: a square post has to fit corner to corner, so the hole must be wider than the post's diagonal (about 1.41 times its width). The calculator stops with an error when it is not.
Gravel, mix type and finishing the top
- Gravel base: a layer of gravel under the post lets water drain away from the end grain. The calculator subtracts it from the concrete. Ten holes with 6 in of gravel take about 2.7 ft³ of gravel. Filling the full 30 in with concrete instead would take 34 bags of 50 lb mix rather than 28. For bulk stone, use the gravel calculator.
- Fast-setting or regular: fast-setting post mixes set in a short time and some are poured dry into the hole and then soaked. Regular concrete is mixed first and gives you longer to plumb the post. Follow the directions on the bag for water, set time and when the post can take a load. Use that bag's yield if it differs from the ones above.
- Slope the top: finish the concrete slightly above the soil and slope it away from the post so rain runs off instead of pooling against the wood.
- Round posts: pick the round shape and enter the post's diameter. The calculator subtracts a circle instead of a square.
Compared with the fence calculator
The fence calculator uses a flat allowance of 2 bags of 80 lb concrete per post, so ten posts get 20 bags. This calculator, with the same ten posts in 10 × 30 in holes, needs 17 bags of 80 lb (1.69 per hole). The flat allowance is a little generous for that hole. It runs short once holes get bigger: a 10 × 36 in hole takes 2.11 bags and a 12 × 36 in hole takes 3.21. Use the fence calculator for the post count and this one for the concrete.
Related jobs
- Deck footings poured in cardboard tube forms: use the Sonotube calculator.
- Decking boards, joists and screws for the deck on top: use the deck calculator.
- Not included here: the posts, brackets, rebar and the gravel itself. For every other pour, see the concrete and masonry calculators.
Frequently asked questions
How many bags of concrete do I need per fence post?
A 4×4 post in a 10 in hole 30 in deep with 6 in of gravel takes about 2.7 bags of 50 lb concrete or 1.7 bags of 80 lb, including 10% waste. For ten posts, buy 28 bags of 50 lb or 17 of 80 lb.
How many bags of concrete for a 6×6 post?
A 6×6 post in a 16 in hole 36 in deep, on 6 in of gravel, takes about 5.4 bags of 80 lb concrete per hole. Ten of them need 55 bags of 80 lb or 87 bags of 50 lb.
How deep should a fence post hole be?
A common rule is a third to a half of the post's height above ground, which is 24 to 36 in for a 6 ft fence, and below the frost line where the ground freezes. Your building department sets the frost depth. A 10 in hole 36 in deep takes about 3.4 bags of 50 lb concrete.
How wide should a post hole be?
About 3 times the post width is a common rule: 10.5 in for a 4×4 and 16.5 in for a 6×6. The calculator warns below about 2.5 times, for example an 8 in hole around a 4×4 (2.29 times).
Should I put gravel in the bottom of a post hole?
Gravel under the post helps water drain away from the end of the post, and it reduces the concrete you need. With 6 in of gravel, ten 10 × 30 in holes take 28 bags of 50 lb concrete and about 2.7 ft³ of gravel. Without gravel they take 34 bags.
Is fast-setting concrete good for fence posts?
Fast-setting mixes are popular for fence posts because they set quickly and some go in dry. Regular concrete gives more working time. Follow the bag directions either way, and check the yield on the label. At 0.375 ft³ per 50 lb bag, the default ten posts need 28 bags.
The formula, worked example and tables on this page are generated from the same calculation engine as the calculator, which is checked by automated reference tests. Last reviewed 20 November 2026 by the Solosoft team. Results are planning estimates, not engineering or code approval. See the calculation disclaimer.