How to calculate concrete cost
The calculator starts with example prices: $165 per cubic yard of ready-mix, a $75 short-load fee on orders under 5 yd³, and $6.50 per 80 lb bag. They are placeholders that show the method. They are not national averages or current market prices. Prices vary by region, plant, mix and season, so replace them with quotes from your local ready-mix plant and building supply store before you rely on the result.
- Measure the slab. The example is 20 × 20 ft, or 400 ft², and 4 in thick.
- Work out the volume: 20 × 20 × 4 ÷ 12 = 133.33 ft³.
- Add 10% waste and divide by 27 to get cubic yards: 133.33 × 1.10 ÷ 27 = 5.43 yd³.
- Round up to the next ¼ yd³, the order step the calculator assumes: order 5.5 yd³. Ask your plant for its own step.
- Check the short-load rule: 5.5 yd³ is not under 5 yd³, so no short-load fee applies.
- Multiply by the price per yard: 5.5 × $165 = $907.50, or $2.27 per ft².
- Compare bags: 245 bags of 80 lb × $6.50 = $1,592.50, or $3.98 per ft².
cost = (L × W × T ÷ 12 × (1 + waste) ÷ 27, rounded up to ¼ yd³) × price per yd³ + fees
Waste goes in before the rounding. Running short in the middle of a pour means a second truck, often with its own short-load fee, and a weak joint where the late concrete meets concrete that has started to set. Ordering a little extra is usually the cheaper mistake.
Ready-mix cost for common slab sizes
The table prices slabs 4 inches thick at the example prices. It shows the volume with waste, the order after rounding and whether the short-load fee applies.
| Slab | Concrete incl. 10% waste | Order | Short-load fee | Ready-mix total | Per ft² |
|---|---|---|---|---|---|
| 10 × 10 ft | 1.36 yd³ | 1.5 yd³ | $75 | $322.50 | $3.23 |
| 12 × 12 ft | 1.96 yd³ | 2 yd³ | $75 | $405.00 | $2.81 |
| 10 × 20 ft | 2.72 yd³ | 2.75 yd³ | $75 | $528.75 | $2.64 |
| 16 × 16 ft | 3.48 yd³ | 3.5 yd³ | $75 | $652.50 | $2.55 |
| 12 × 24 ft | 3.91 yd³ | 4 yd³ | $75 | $735.00 | $2.55 |
| 20 × 20 ft | 5.43 yd³ | 5.5 yd³ | None | $907.50 | $2.27 |
| 24 × 24 ft | 7.82 yd³ | 8 yd³ | None | $1,320.00 | $2.29 |
| 30 × 30 ft | 12.22 yd³ | 12.25 yd³ | None | $2,021.25 | $2.25 |
Example prices: $165/yd³ and a $75 fee on orders under 5 yd³, with no delivery charge. Replace them with your local quote in the calculator.
Small orders pay the fee on top of the concrete, so they cost more per square foot. The 10 × 10 ft slab costs $3.23 per ft², against $2.27 for the 20 × 20 ft slab. The largest slab in the table that still pays the fee is 12 × 24 ft, at 4 yd³. If your plant's threshold or fee is different, enter yours in the calculator.
Ready-mix or bags: where bags stop being cheaper
Bags have no order step and no short-load fee, so they win on very small pours. As the pour grows, bags add cost one bag at a time, while ready-mix adds it in ¼-yard steps on top of a fixed fee.
| Slab | Concrete incl. 10% waste | 80 lb bags | Bag cost | Ready-mix incl. fees | Cheaper |
|---|---|---|---|---|---|
| 4 × 4 ft | 0.22 yd³ | 10 | $65.00 | $116.25 | Bags |
| 6 × 6 ft | 0.49 yd³ | 22 | $143.00 | $157.50 | Bags |
| 7 × 7 ft | 0.67 yd³ | 30 | $195.00 | $198.75 | Bags |
| 8 × 8 ft | 0.87 yd³ | 40 | $260.00 | $240.00 | Ready-mix |
| 10 × 10 ft | 1.36 yd³ | 62 | $403.00 | $322.50 | Ready-mix |
| 12 × 12 ft | 1.96 yd³ | 88 | $572.00 | $405.00 | Ready-mix |
| 16 × 16 ft | 3.48 yd³ | 157 | $1,020.50 | $652.50 | Ready-mix |
| 20 × 20 ft | 5.43 yd³ | 245 | $1,592.50 | $907.50 | Ready-mix |
Example prices: $6.50 per 80 lb bag, $165/yd³ of ready-mix and a $75 fee under 5 yd³. Material only.
At the example prices, bags are cheaper up to about a 7.5 × 7.5 ft slab 4 inches thick (0.76 yd³ with waste). From about 8 × 8 ft (0.87 yd³) up, ready-mix costs less. Change the prices and the crossover moves. A bigger short-load fee or cheaper bags push it toward larger pours. Pricier bags pull it toward smaller ones.
Price is not the only test. Past about 1 yd³, hand mixing gets slow, and the first batches can start to set before the last are placed. If you go with bags, the concrete bag calculator counts bags and their total weight for 40 to 80 lb sizes. Some plants also have a minimum order or charge extra for very small loads, so ask before you plan on a fraction of a yard.
Concrete cost per square foot by thickness
Thicker slabs take more concrete for every square foot. The table shows ready-mix cost per ft² at the example prices, with the short-load fee included where it applies.
| Slab | 4 in thick | 5 in thick | 6 in thick |
|---|---|---|---|
| 10 × 10 ft | $3.23 | $3.64 | $4.46 |
| 12 × 12 ft | $2.81 | $3.39 | $3.96 |
| 20 × 20 ft | $2.27 | $2.89 | $3.40 |
| 24 × 24 ft | $2.29 | $2.86 | $3.37 |
| 30 × 30 ft | $2.25 | $2.84 | $3.39 |
Includes 10% waste and rounding to ¼ yd³. Concrete only: no base, forms, reinforcement or labor.
On the 20 × 20 ft slab, going from 4 to 6 inches raises the ready-mix cost from $907.50 to $1,361.25. According to the 2021 International Residential Code (Section R506.1), a concrete floor slab on the ground must be at least 3½ inches thick. Driveways, garage floors and slabs under heavy loads are often poured thicker. Take the thickness from your plans or your building department.
What moves the price of concrete
The price in a quote depends on more than volume. Each plant prices these items differently, so ask about each one and fold the answers into the calculator.
- Strength and mix: ready-mix is usually ordered by compressive strength in psi. Higher-strength mixes use more cement and cost more per yard. Your plans or local code may set a minimum strength for slabs, driveways and footings.
- Fiber and admixtures: fiber, accelerators for cold weather, retarders for hot weather, air entrainment where slabs face freezing and thawing, and color all add to the price per yard.
- Short loads: many plants add a fee below a set load size. Some charge a flat fee and some charge for each yard short of the threshold. The calculator adds a flat fee, so turn a per-yard charge into a total and enter that.
- Delivery distance: plants often price by zone or charge more for long hauls. Enter any delivery or fuel charge in the fees field.
- Time: after-hours, weekend and holiday pours usually cost more. Ask how much unloading time is included and what extra time on site costs.
- Placement: if the truck cannot reach the forms, you need a pump, a conveyor or a wheelbarrow crew. A pump is billed separately from the concrete.
Not included in the estimate
- Base: the compacted gravel under the slab. Size it with the gravel calculator.
- Forms: form boards, stakes and form release.
- Reinforcement: rebar or wire mesh. Count bars and weight with the rebar calculator.
- Finishing and labor: placing, screeding, finishing, control joints, curing and sealing, plus any pump, permit or inspection.
- Other shapes: this calculator prices rectangular slabs. For footings, walls and steps, get the volume from the concrete calculator and multiply by your price per yard. For the rest of the job, see the concrete and masonry calculators.
Frequently asked questions
How much does a 20 × 20 concrete slab cost?
At the example prices of $165 per yard, a 20 × 20 ft slab 4 inches thick needs a 5.5 yd³ order and costs $907.50 in ready-mix. At 6 inches it needs 8.25 yd³ and costs $1,361.25. That is concrete only. Replace the example price with your local quote for a real figure.
How much concrete do I need for a 10 × 10 slab?
A 10 × 10 ft slab 4 inches thick takes 1.36 yd³ with 10% waste, so you order 1.5 yd³. At the example prices that is $247.50 of concrete plus the $75 short-load fee, or $322.50 in total. The same slab takes 62 bags of 80 lb, $403.00 at $6.50 a bag.
Is it cheaper to buy bags or ready-mix concrete?
Bags are cheaper for small pours and ready-mix for large ones. At the example prices the switch comes between a 7.5 × 7.5 ft and an 8 × 8 ft slab 4 inches thick, around 0.76 to 0.87 yd³. Run your own prices through the calculator, because the short-load fee moves that point a lot.
What is a short-load fee for concrete?
It is a charge a ready-mix plant adds when an order is smaller than a set load size, to cover a truck making the trip part full. The calculator's example is $75 on orders under 5 yd³, which a 12 × 24 ft slab at 4 inches still pays. Ask your plant for its real threshold and fee.
How much does a concrete slab cost per square foot?
At the example prices, ready-mix for a 20 × 20 ft slab costs $2.27 per ft² at 4 inches and $3.40 at 6 inches. Small slabs cost more per ft² because of order rounding and the short-load fee. These figures are material only, with no base, forms, reinforcement or labor.
How much extra concrete should I order?
Add about 10% for spillage, an uneven base and form bulge, then round up to the plant's order step. For the 20 × 20 ft slab, 133.33 ft³ of net volume becomes 5.43 yd³ with waste and a 5.5 yd³ order.
The formula, worked example and tables on this page are generated from the same calculation engine as the calculator, which is checked by automated reference tests. Last reviewed 20 November 2026 by the Solosoft team. Results are planning estimates, not engineering or code approval. See the calculation disclaimer.